+8613639422395

Safety and environmental protection measures for concrete engineering construction

Sep 26, 2025

Safety environmental protection measures for concrete engineering construction

 

 

Concrete engineering construction needs to take into account both safety control and environmental protection governance, and both should run through the entire process of "construction preparation - process implementation - post-construction closure". Safety measures focus on preventing accidents such as collapses, falls from heights, and mechanical injuries, while environmental protection measures target pollution issues such as noise, dust, wastewater, and solid waste. The specific plans are as follows:

I. Safety Measures for Concrete Engineering Construction (Core Risk Prevention and Control

Safety measures should revolve around the five elements of "people, machinery, materials, methods, and environment", and formulate control plans for high-risk points in key operation links (mixing, transportation, pouring, and curing). The core contents are as follows:

1.Prevention and control of collapse accidents (the most critical risk)

The main risks of collapse come from formwork supports, deep foundation pits, and instability of concrete structures. It is necessary to control the entire chain from "design - erection - monitoring".
Preliminary design: For high formwork (height ≥8m) and deep foundation pits (depth ≥5m), a specialized plan must be provided by a professional unit. The bearing capacity of the vertical rods, the spacing of the horizontal rods, and the strength of the support structure should be calculated.
The plan can only be implemented after being approved by experts.

Installation and control: Wooden pads or steel sections should be placed at the bottom of the support poles (to prevent foundation settlement). The ground clearance poles should be no more than 20cm from the ground, and the verticality deviation of the poles should be no more than 1/1000. The slope of the foundation pit should be laid out according to the plan (in soft soil areas, steel sheet piles and soil nail walls should be used for support). Over-digging or overloading is strictly prohibited (no materials should be piled up within 1.2 meters from the edge of the pit).
Pouring and dismantling: Concrete pouring should follow the principle of "layering and symmetry", with the thickness of each layer not exceeding 30cm (for pumped concrete). It is strictly prohibited to pour on one side in a concentrated manner to prevent the support from being biased. Before the formwork is removed, the concrete strength needs to be tested (with test blocks under the same conditions). The beams and slabs can be removed only when they reach 75% of the designed strength and the cantilever components reach 100%. The removal sequence follows the principle of "remove the later supports first and then the later supports".
Deformation monitoring: For high formwork and deep foundation pits, daily monitoring of settlement and displacement (using a total station or level) is conducted. The warning values are set as settlement ≥10mm and displacement ≥5mm. Work should be immediately halted for rectification once the warning is exceeded.

2. Prevention and control of falls from heights and object strikes

Standardization of protective facilities: For high-altitude pouring platforms (such as floor slabs and beams), a 1.2-meter-high guardrail (with a crossbar spacing of no more than 60cm) is set up, an 18-cm-high toe board is installed at the bottom, and a close-mesh safety net (flame-retardant type, mesh density ≥2000 mesh / 100cm²) is hung on the outside. Elevator shafts and reserved openings shall be sealed with "tool type" (steel mesh + steel plate cover plate), and it is strictly prohibited to temporarily block them.
Personnel operation norms: Workers engaged in high-altitude operations must wear "double-hook safety belts" and use them "high and low" (the hanging point should be higher than the working surface). It is strictly prohibited to walk on the edges of unprotected beams and slabs. The scaffold boards on the working layer should be fully laid, and the probe boards (extending more than 15cm beyond the crossbars) need to be fixed or removed. When performing cross-operation, a horizontal safety protection layer (such as a safety flat net) should be set in the middle, with a spacing of no more than 10 meters.
Material management: The stacking volume of materials on the aerial platform should not exceed the load limit (controlled at 50% of the design value). Tools should be placed in dedicated tool bags, and it is strictly prohibited to throw waste materials. When a tower crane is transporting concrete hoppers, the hoppers need to be covered and a warning area (isolated by warning tape) should be set up below. Unrelated personnel are prohibited from entering.

3. Mechanical Injury and electric shock prevention and control

Mechanical safety control: Fixed protective covers should be installed on the transmission parts (gears, belts) of concrete mixers and vibration rods. The strength of the protective covers must be impact-resistant. Steel plates (with an area of ≥0.5 square meters) should be placed under the outriggers of the pump truck. Before operation, make sure the outriggers are stable. No one is allowed to stand within the rotation radius of the fabric rod. Equipment operators must hold special operation certificates to work. It is strictly prohibited to operate without a certificate or after drinking alcohol. When cleaning the mixer, it must be "powered off and locked" (with a warning sign), and supervised by a designated person.
Temporary power safety: The construction site adopts the "three-phase five-wire system", and follows the principle

II. Environmental Protection Measures for Concrete Engineering Construction (Pollution Source Control)

Concrete construction is prone to generating four types of pollution: noise, dust, wastewater and solid waste. It is necessary to achieve environmental protection compliance through "source reduction, process control and end-of-pipe treatment". The specific measures are as follows:

1. Noise pollution control (daytime ≤70dB, nighttime ≤55dB)

Noise reduction for equipment: The mixing plant is equipped with a sound insulation shed (using color steel plates + sound insulation cotton, with a thickness of ≥10cm), and low-noise vibration rods (noise ≤85dB) are selected. Mufflers are installed on the engines of pump trucks and tank trucks. Construction is prohibited at night (22:00-6:00). If construction is necessary, a night construction permit must be obtained and the surrounding residents must be informed in advance.
Operation control: Concrete pouring should be concentrated during the day as much as possible, and vibration operations at night should be reduced. Sound insulation barriers (with a height of ≥2.5m, built with bricks or color steel sandwich panels) are set up at the boundary of the construction site, and the bottom of the barriers is sealed (to prevent noise leakage). After entering the site, the speed limit for transport vehicles should be no more than 5km/h and honking is prohibited (only in emergency situations).

2. Dust pollution control (hourly average PM10 ≤150μg/m³)

Dust prevention in mixing plants: Powder materials such as cement and fly ash are stored in closed tanks, and dust removal devices (such as pulse bag filters) are installed on the top of the tanks. The aggregate storage yard is equipped with a closed material shed (the shed roof is made of steel structure + color steel plate), and a sprinkler system is installed inside the shed (spray once every two hours, each time for 30 minutes) to prevent the aggregates from generating dust.
Transportation and pouring dust prevention: When concrete is transported by tank trucks, dust covers should be added to the tank mouth (to prevent slurry from spilling), and the vehicle body should be regularly washed (tires and the vehicle body should be washed before leaving the factory to avoid driving with mud). The main roads at the construction site are hardened (using C20 concrete with a thickness of ≥15cm), and sprinklers or fog cannons are set up on both sides of the roads (spraying once per hour to suppress dust). When pouring concrete, lay colored tarpaulin under the pump truck's material rod to prevent the cement slurry from dripping and polluting the ground. Clean it up in time after the operation.

3. Wastewater pollution control (Discharge after meeting standards, COD≤500mg/L)

Wastewater collection: The mixing plant is equipped with a sedimentation tank (three-stage sedimentation, with a total volume of ≥50m³). The wastewater used for rinsing the mixer and tank trucks is treated in the sedimentation tank and reused (for aggregate spraying and road watering). Direct discharge is strictly prohibited. Drainage ditches (with a slope of ≥3‰) are set up at the construction site to direct rainwater and pouring wastewater into sedimentation tanks, preventing sewage from overflowing.
Treatment and reuse: The sedimentation tank is regularly dredged (once a month), and the dried sludge is disposed of together with construction waste. The water used for concrete curing is treated by spray curing (to avoid water accumulation), and the curing wastewater is recycled to the sedimentation tank through the drainage ditch, achieving "zero discharge". It is strictly prohibited to mix oil stains (such as waste oil from equipment maintenance) into wastewater. Oil stains must be collected separately and handed over to qualified units for treatment.

4. Solid waste pollution control (classified disposal, recovery rate ≥90%)

Solid waste classification: Concrete waste residues (such as leftover concrete from pouring and waste from formwork cleaning) are collected separately. The usable parts (such as intact concrete blocks) can be crushed and used as roadbed fillers. The packaging bags (cement bags, admixture bags) are collected centrally and handed over to the waste recycling station for processing. Classified garbage bins (recyclable and non-recyclable) are set up for domestic waste, which are regularly removed by the sanitation department.
Reduction measures: Accurately calculate the dosage before concrete mixing and reduce the remaining amount according to the principle of "mixing as needed". The formwork adopts recyclable steel formwork (replacing wooden formwork), reducing wood waste. During construction, optimize the pouring plan to avoid rework due to missed vibration and misalignment of platforms, and reduce the generation of waste residue.

III. Synergistic Management of Safety and Environmental Protection (Long-Term Guarantee Mechanism

Education and training: Personnel entering the site must undergo dual training on "safety and environmental protection", and can only take up their posts after passing the assessment. Special operation personnel (mixers, scaffolders, electricians) need regular refresher training to master the latest safety regulations and environmental protection requirements.
On-site inspection: Safety officers and environmental protection officers conduct joint daily inspections, focusing on checking the stability of supports, the integrity of protective facilities, noise and dust monitoring data, and the reuse of wastewater. Any issues found are immediately addressed with rectification notices and followed up for a closed loop.
Emergency management: Develop special emergency plans for safety and environmental protection (such as collapse rescue and handling of excessive dust), equip with emergency supplies (such as first aid kits, fog cannons, sandbags), and organize drills every quarter to ensure rapid response to emergencies.

 

Through the above measures, it is possible to achieve "zero safety accidents and zero environmental over-limit" in concrete engineering construction, taking into account both project quality and ecological protection.

 

Note: The parameters provided in this document are for reference only and are not mandatory. Due to differences in technical characteristics between different brands and models of laser levelers, please consult the manufacturer for a suitable solution before actual operation. This reference document assumes no responsibility for any issues arising from failure to follow the manufacturer's instructions.
 

 
 
Our factory
 

Shandong Vanse Machinery Technology Co.,Ltd

company
 
after-sales service
 
construction site from all the world
 
Click the below to jump immediately!!!
AMOUR JOINT

ARMOUR JOINT

CONCRETE LASER LEVELING MACHINE

CONCRETE LASER LEVELING MACHINE

POWER TROWEL

POWER TROWEL

SLIPFORM MACHINE

SLIPFORM MACHINE

STEEL FIBER

STEEL FIBER

TOPPING SPREADER

TOPPING SPREADER

 

Thanks to all the friends who support and trust Shandong Vanse Machinery Technology Co., Ltd.
If you want to know more about Shandong Vanse Machinery Technology Co., Ltd. or have any questions, please feel free to contact us:
• Tel: +86-13639422395
• Email: sales@vanse.cc
• Website: www.vansemac.com

Send Inquiry