+8613639422395

What are the countermeasures for common safety issues in concrete engineering construction?

Sep 26, 2025

What are the countermeasures for common safety issues in concrete engineering construction

 

 

Concrete engineering construction involves multiple links such as material transportation, mixing, pouring and curing. The working environment is complex (such as high-altitude, edge and heavy machinery operation), which is prone to cause safety accidents such as collapse, fall from height and mechanical injury. For common safety issues, response measures should be formulated throughout the entire process of "prevention - control - emergency response". Specifically, they can be classified by risk types as follows:

 

I. Collapse Accident: Concrete structure/Support/formwork collapse (the most serious risk)

Common causes

The spacing of the vertical rods of the formwork support is too large, there is no base plate at the bottom of the vertical rods/the foundation is unstable.
Improper sequence of concrete pouring (such as not pouring in layers, resulting in local load exceeding the limit);
The formwork was removed too early (the concrete strength did not meet the design requirements).
The foundation pit/slope support was inadequate, causing deformation due to the load of concrete pouring.

Countermeasures

Preliminary design and verification

The formwork support and scaffolding must be designed by professionals in accordance with the specifications, calculating the load-bearing capacity of the vertical rods, the spacing of the horizontal rods, and the setting of the sweeping rods to ensure the anti-overturning and anti-deformation capabilities.
The foundation pit/slope support plan should be specially designed in combination with geological conditions (such as soft soil and quicksand layers). When necessary, support forms such as sheet piles and soil nail walls should be adopted. Over-excavation is strictly prohibited.

Construction process control

Before setting up the support, the foundation should be leveled and compacted. Wooden pads or steel sections should be placed at the bottom of the vertical poles to prevent uneven settlement.
Concrete pouring should follow the principle of "layering, symmetry and gradual progress". The thickness of each layer should not exceed 30cm (for pumped concrete). It is prohibited to stack materials on one side or pour them in a concentrated manner, which may cause the support to be biased.
Before the formwork is removed, the concrete strength must be tested (by the rebound method or the same condition test block test). It can only be removed when it reaches 75% (for beams and slabs) or 100% (for cantilever components) of the designed strength, and the removal sequence follows the principle of "remove the later supports first, and then remove the later supports".

Monitoring and Early Warning

For high formwork (height ≥8m) and deep foundation pits (depth ≥5m), "deformation monitoring" should be implemented. Daily data on the settlement of supports and slope displacement should be recorded. Work should be immediately halted for rectification if the warning values are exceeded (such as settlement ≥10mm).
 

II. Falls from Heights: Falls from edge work or high-altitude operations

Common causes

The pouring platform and scaffolding have no guardrails or toe boards, or the height of the guardrails is insufficient (less than 1.2 meters).
The worker is not wearing a safety belt, or the safety belt is not fastened to a secure support point.
No closed protection or warning signs have been set up at the edge openings (such as elevator shafts and stairwells).

Countermeasures

Standardization of protective facilities

For high-altitude pouring platforms (such as floor slab and beam pouring), 1.2-meter-high guardrails must be set up, with 18-cm-high toe boards at the bottom, and close-mesh safety nets (flame-retardant type) hung on the outside of the guardrails.
Elevator shafts and reserved openings shall be sealed with "tools" (such as steel mesh + cover plates), and it is strictly prohibited to temporarily block them with debris.
The scaffold working layer is fully covered with scaffold boards, with no gaps between the boards. The probe boards (extending more than 15cm beyond the crossbars) must be fixed or removed.

Personnel operation specifications

Workers engaged in high-altitude operations must wear "double-hook safety belts" and use them "high up and low down" (the safety belt's hanging point should be higher than the work position). It is strictly prohibited to walk on the edges of unprotected beams and slabs.
Before starting work, check the integrity of protective facilities. If loose railings or damaged safety nets are found, stop work immediately for repair.
High-altitude concrete pouring operations are prohibited in severe weather conditions such as heavy rain and winds above level 6.

 

III. Mechanical injury accidents: Injuries caused by mixing, transportation or vibration equipment

Common causes

The concrete mixer and vibrator have no protective cover or the protective cover is damaged.
The equipment operators work without a license and operate in violation of regulations (such as cleaning the residue in the mixer by hand).
There are irrelevant personnel staying within the working radius of pump trucks or tank trucks, causing collisions or crushing.

Countermeasures

Intrinsic safety of equipment

The transmission parts of the mixing plant and vibration equipment (such as gears and belts) must be equipped with "fixed protective covers", and the strength of the protective covers must meet the requirements of impact resistance.
The material rods and outriggers of the concrete pump truck are equipped with "limit alarm devices", and steel plates are placed under the outriggers (to prevent subsidence). Before operation, make sure the outriggers are stable.
Before using the equipment, conduct a "pre-shift inspection", with a focus on checking the braking, steering and leakage protection devices. Do not start the equipment if they are not up to standard.

Personnel and on-site control

Equipment operators must pass training and assessment and hold a "Special Operations Operator Certificate" to work. It is strictly prohibited to operate without a certificate or after drinking alcohol.
When cleaning or maintaining the mixer, it must be "powered off and locked" (with a warning sign), and there must be a dedicated person to supervise. Live operation is strictly prohibited.
The operation areas of pump trucks and tank trucks are set up with "warning zones" (isolated by warning tapes or guardrails), and irrelevant personnel are prohibited from entering. Drivers should observe the surrounding environment before operation.

 

IV. Electric Shock Accidents: Vibration/Lighting/temporary power leakage

Common causes

The cables of mobile equipment such as vibration rods and water pumps are damaged and the insulation layer is aged.
The temporary power supply did not adopt the "three-phase five-wire system", and the grounding and zero connection protection was missing.
Waterproof electrical appliances were not used in damp environments (such as pouring basements or working during the rainy season).

Countermeasures

Standardization of temporary electricity usage

Temporary power supply at the construction site must be laid by professional electricians, strictly adhering to the principle of "one machine, one switch, one leakage protector, one box" (each device is equipped with an independent switch and a leakage protection device). The operating current of the leakage protection device should be ≤30mA, and the operating time should be ≤0.1s.
The cables of mobile devices shall adopt "wear-resistant and waterproof rubber-sheathed cables". It is strictly prohibited to drag or crush the cables. The cable joints shall be sealed with waterproof tape.
Distribution boxes and switch boxes should be installed in dry and rain-proof locations. The grounding resistance of the box body should be no more than 4Ω. The box door should be locked and a "Electrical Safety Sign" should be affixed.

Working environment and operation protection

When working in a damp environment, operators should wear "insulating shoes" and "insulating gloves", and insulating sleeves should be added to the handles of the vibration rods.
Lighting fixtures should use "36V safe voltage" (such as in basements and deep well pouring), and the use of 220V ordinary bulbs is strictly prohibited.
Regularly test the insulation resistance of temporary power lines. Replace the cables immediately when the insulation value is lower than 0.5MΩ.

 

V. Object strike accidents: Injuries caused by falling materials

Common causes

The tools and materials piled up on the concrete hopper and scaffolding were not fixed and fell, injuring the people below.
Workers working at heights randomly throw tools and waste materials (such as bolts and broken formwork).
There is no horizontal protective layer for cross-operation (such as pouring above and cleaning below).

Countermeasures

Material management

The amount of concrete and tools stacked on the aerial work platform shall not exceed the load-bearing limit of the platform, and they shall be firmly fixed (such as binding the hopper with iron wire).
It is prohibited to stack irrelevant sundries on scaffolding and formwork. After work, waste materials should be cleared in time to avoid accumulation.
When transporting materials vertically (such as using a tower crane to transport concrete hoppers), the hoppers must be covered, overloading is strictly prohibited, and a "warning zone" should be set up below.

Cross-operation protection

When performing cross-operation up and down, a "horizontal safety protection layer" (such as fully laid scaffolding boards or safety flat nets) should be set in the middle, and the spacing between the protection layers should not exceed 10 meters.
Workers working at heights are strictly prohibited from throwing any objects downward. Tools should be placed in tool bags to prevent them from falling.
The personnel working below must wear "safety helmets", with complete brims and chin straps, and the chin straps must be fastened tightly.

 

VI. Emergency Support: Rapid response after an accident occurs

Emergency preparedness

The construction site is equipped with a "first aid kit" (including tourniquets, bandages, fracture fixation splints, etc.), and 1-2 part-time first aid workers are trained.
Special emergency response plans should be formulated for accidents such as collapses and electric shocks. An emergency drill should be organized once every quarter to ensure that personnel master escape and first aid skills.
An "emergency passage" is set up on site, with a width of no less than 1.2 meters and no debris blocking it. Emergency lighting (automatically activates after power failure) covers key areas.

Principles of Accident Handling

When a collapse occurs, immediately stop the operation, organize personnel to evacuate to a safe area, and strictly prohibit blind rescue (to prevent secondary collapse). At the same time, contact professional rescue teams (such as the fire department).
When an electric shock occurs, first "cut off the power supply" or use an insulating tool to remove the injured person from the power source, and then perform cardiopulmonary resuscitation (send to the hospital if necessary).
When mechanical injury occurs, immediately stop the operation of the equipment, stop bleeding and bandage the wound. For those with fractures, avoid moving them at will and send them to the hospital promptly.

 

Summary: Core principles

The safety management of concrete engineering should adhere to the principle of "prevention first and combination of prevention and control". Through the triple guarantee of "technical measures (such as support verification, protective design) + management measures (such as personnel training, on-site inspection) + emergency measures (such as plan drills, first aid preparations)", risk control should be integrated throughout the entire construction process, and at the same time, the safety awareness of all personnel should be strengthened. Eliminate the "three violations" behaviors of "illegal command, illegal operation and violation of labor discipline", and reduce the occurrence of safety accidents from the root.
 

Note: The parameters provided in this document are for reference only and are not mandatory. Due to differences in technical characteristics between different brands and models of laser levelers, please consult the manufacturer for a suitable solution before actual operation. This reference document assumes no responsibility for any issues arising from failure to follow the manufacturer's instructions.
 

 
 
Our factory
 

Shandong Vanse Machinery Technology Co.,Ltd

company
 
after-sales service
 
construction site from all the world
 
Click the below to jump immediately!!!
AMOUR JOINT

ARMOUR JOINT

CONCRETE LASER LEVELING MACHINE

CONCRETE LASER LEVELING MACHINE

POWER TROWEL

POWER TROWEL

SLIPFORM MACHINE

SLIPFORM MACHINE

STEEL FIBER

STEEL FIBER

TOPPING SPREADER

TOPPING SPREADER

 

Thanks to all the friends who support and trust Shandong Vanse Machinery Technology Co., Ltd.
If you want to know more about Shandong Vanse Machinery Technology Co., Ltd. or have any questions, please feel free to contact us:
• Tel: +86-13639422395
• Email: sales@vanse.cc
• Website: www.vansemac.com

Send Inquiry